HANCOCK – The Upper Delaware Council, Inc. delivered testimony at a public hearing convened by the New York State Department of Public Service in Hancock to gather input on the application by New York Regional Interconnect, Inc. (NYRI) to construct a high voltage direct current transmission line on a 190-mile path between Marcy and Rock Tavern, NY.
The New York State Public Service Commission (PSC) will determine by August of 2009 whether to grant NYRI a Certificate of Environmental Compatibility and Public Need for its proposed $2.1 billion power line.
The two Administrative Law Judges assigned to the case, Jeffrey Stockholm and Michelle Phillips, agreed to hold 13 public information forums between October 20 and November 6 in the seven New York State counties affected by the proposed route to personally hear statements and create a record for their review.
The UDC was represented at three of the hearings which took place on Oct. 29 at the Delaware Community Center in Callicoon and Sullivan West Central High School in Lake Huntington, and on Nov. 5 at Hancock Central School in Hancock.
“Page 134 of the River Management Plan states that new, major electric lines with a design capacity of 125 kilovolts or greater and extending a distance of ten miles or more in length are an ‘incompatible use’ anywhere in the river corridor”, testified UDC Executive Director Bill Douglass.
(Click to read entire article)
Blog Archive
-
?
2008
(616)
-
?
November
(12)
- $19,000 Electric Car Coming to US in May 2009: Int...
- Iberdrola begins acquisition
- Massa accepts election victory
- DEC Taking Comments On Natural Gas Drilling
- State urged not to stifle gas drilling
- First gas-drilling sites around the Southern Tier ...
- Mini nuclear plants to power 20,000 homes
- NYRI is blasted at state hearing
- UDC opposes NYRI power line
- Futuristic-Looking LED Bulbs
- RG&E launches Voice Your Choice campaign
- Natural gas reserves in Marcellus shale larger tha...
-
?
November
(12)